    Use Plan & Progress on a site to agree what has to be built, report what was done each day and see how far the work is. Managers set up and change the plan. Managers, site foremen and office can read it. Workers and clients do not see it.

    Setting up the baseline

    On the Work plan tab, the approved version shows a short header (version and approval date, planned work period, planned workforce, number of work items) and every approved work item in its saved order, grouped by location. Each item shows its trade and planned quantity, its number of checkpoints, or "Tracked by status". Open Weighting and checkpoints or Calculation and source for details. When a draft exists, the editable draft comes first and the approved version, still in force, can be opened below it as read-only.

    1. Open the site and choose the Plan & Progress tab. Press Start the plan.
    2. Under Project setup, enter the start date, the planned end date, how many people you plan for, and pick the planned workers. Press Save setup.
    3. Add work items. For each item give a name, location, trade and how it is measured:
      • Quantity: planned quantity and unit, for example 200 m².
      • Verifiable checkpoints: steps that can be checked, each with a share, for example delivered 30 % and installed 70 %. The shares must total 100 %.
    4. Give each included item a weight. The weights must total exactly 100 %. Distribute equally fills them in for you. Untick Include in overall progress for items you only want to track.
    5. Press Approve baseline. The button stays off and lists what is missing until everything is complete.

    Proposing items from a document (optional)

    In the draft, Propose items from a document can read a bill of quantities, schedule or scope description for you.

    1. Choose a site document, or press Upload a document (PDF, Word, Excel, CSV or text).
    2. Press Read with AI. Your company's AI limits and monthly budget apply, as for any file read.
    3. Each proposal shows where it was found in the document and the quoted text. A planned quantity is filled in only when the document prints it, or when it can be calculated from the measurements and deductions printed for that element. Otherwise the field stays empty for you.
      • The calculation box shows the printed dimensions, the gross quantity, each deduction with its label and the net quantity. A printed net quantity is never reduced again.
      • A short check says whether the printed numbers add up. If they differ, both values stay visible for your review; neither is replaced.
      • Empty cells and dashes are not read as zero, unless the document's legend says they mean zero.
      • A printed total row only checks the rows above it and is never added as a work item. If you accept only some rows, the check shows an incomplete selection, not a calculation error.
    4. Check and edit each proposal, then press Accept into draft or Reject. Nothing is added to the plan until you accept it.

    If you change a quantity taken from the document, BauBau asks for a reason.

    After you accept a proposal, open Calculation and source on the work item. It shows the calculation as read from the document, the document and quoted text, and the quantity history: who changed which value, when and why. It stays available after the baseline is approved.

    Reading the same document again fills in quantities that were missing and does not add items twice. For drawings and dimensioned sketches use a PDF; Word and Excel files are read as text only. A measurement that is not written on the drawing is never guessed.

    If the AI read fails, add the work items by hand; everything else works the same.

    An approved baseline cannot be edited. To change it, press Amend baseline: a new draft version is created from the approved one. The old version stays in force until you approve the new one. Progress already reported keeps counting for items that stay in the plan. You cannot change the unit of an existing item or what an existing checkpoint means; add a new item or checkpoint instead.

    Reporting progress

    The Plan tab has two parts: Progress and Work plan. Report with Report progress at the top of Progress, or with + Report on a work item (the item is chosen for you; you can still change it). The form opens at the side, or full screen on a phone. You can also report during Assisted Capture under Report plan progress (optional).

    1. Choose the work item and the date.
    2. Enter the quantity completed by the whole crew, or the checkpoint reached. The quantity is counted once, no matter how many people worked on it.
    3. Pick at least one worker for the crew from the workers selected in the approved plan. Both save buttons stay blocked until someone is chosen. If the plan has no workers, a manager must first add them through a plan amendment and approve it. Earlier reports without crew keep counting; correcting one needs a crew. A correction can also keep the people of the original record, including former workers (shown as "Former worker" when their name is no longer available). Hours are not entered here; they stay in the hours records.
    4. If your note says one exact amount in the item's unit, such as "completed 50 m²", BauBau fills it in as a suggestion. Check it before saving. Notes about planned, remaining, total or approximate amounts (for example "200 m² planned" or "noch 80 m² offen"), several numbers or another work item leave the field empty. Vague notes and photos never produce a number.
    5. Press Save and confirm, or Save for review so another manager confirms it.

    Enter only the work newly done for that date. While you type, BauBau shows an estimate: confirmed so far + this report = new total. It is based on the confirmed quantities loaded now; if you save for review, confirmed progress does not change until a manager confirms it. For a correction the estimate is confirmed so far − the corrected record + the new value. Changing the work item clears the quantity, checkpoint and status (BauBau asks first); date, crew and note stay. Closing the form with entered values asks whether to keep editing or discard.

    Only confirmed records count. Pending review (N) opens every record waiting for confirmation. Submission history lists every record, including corrections, with filters (All, Pending, Confirmed, Rejected, Superseded) that apply to all records; press Load more for older ones. A manager can confirm or reject waiting records, and correct a confirmed one with Correct; the correction stays with the same work item. A correction counts only after it is confirmed; until then the earlier value stays in the totals. The history keeps both.

    Reading progress

    Work items show as cards in one list. Each card shows the status above the title, then the trade, completed and planned quantity, percentage and bar; + Report sits at the top right. If no planned quantity is set, the card says so instead of showing 0; a planned quantity of 0 is shown as 0 and gets no percentage. Each card has two sections you can open separately, both closed at first. Submission history (N) lists every record of that item with the same filters as the full history; N counts all of them (waiting, confirmed, rejected and corrected), not just the ones loaded so far. Items with no submissions yet show no history section. Work item details sits below it and shows Progress share and calculation (the item's share of overall progress and how its percentage is worked out) and, for managers, Calculation and source for the document. Both sections can stay open together, and opening or closing either keeps the history filter you chose. In the "as of" view, cards are labelled with the date and + Report is hidden; item history always shows current records.

    • A quantity item shows the completed share of the planned quantity, up to 100 %. More than planned is flagged.
    • A checkpoint item counts only the checkpoints reached. "In progress" alone adds nothing.
    • The overall percentage is shown only for an approved baseline whose weights total 100 %. If some items are not included, the figure is called Progress of included work and the left-out items are listed.
    • Pick a date under Show progress as of to see the state on that day, with the plan version in force then. Later entries, corrections and amendments are left out.
    • Worker shows only the work items with that worker's confirmed participation. It offers the workers of the plan version shown for the date plus everyone on the confirmed records counted in that view; search by name or worker ID. If the chosen worker is not available for another date, the filter goes back to All workers.
    • Status (after Worker) shows only work items that are Not started, In progress or Done on the date shown. It works together with the other filters, keeps its choice when you change the date, and hides locations with no matching items. If nothing matches, press Clear filters. The figures at the top always cover the whole plan.
    • If progress cannot be loaded, BauBau says so. It never shows 0 % instead.

    In AI answers

    The site assistant and connected assistants can use the approved plan and the confirmed progress when a manager, site foreman or office person asks, and cite the plan and work items. Waiting records do not count. Workers and clients do not get plan or progress information through AI answers. Hours, crew members and money are never part of it.

    Sites with plan history

    A site with an approved plan or confirmed progress cannot be deleted, so its history is kept. If such a site must be closed, ask Support: it is archived and its plan history stays readable.